MID energy meters: what the directive means for meters

MID stands for the European Measuring Instruments Directive 2014/32/EU. Its annex MI-003 defines the requirements an active energy meter must meet so that it may be used for billing without national initial verification: the manufacturer has the type examined (module B) and secures production through a supervised quality system (module D). An MID meter carries the CE marking with the metrology mark; the CELSA MID meters are assessed to modules B+D and measure in class B to EN 50470-3.

MID applies to the meter – not to the measuring chain in front of it. A direct-connected MID meter records consumption for billing as soon as the load current flows through it. If a CT-operated meter measures via current transformers, these must also be approved for billing, such as the calibrated plug-on current transformers ALO-E or the wound-primary WALO-E; the meter converts back to the primary current with the set ratio.

After commissioning the verification period runs: for electronic electricity meters in Germany it is 8 years (Measuring and Verification Ordinance, annex 7), after which the meter is re-verified or replaced. Which series fits which task – direct connection up to 100 A or CT-operated, single- or three-phase, with Modbus, M-Bus, TCP/IP or LoRa – is shown with a selection table on the energy meters product page.

Energy meters compared: direct metering with the load current through the meter and CT metering with a 400/5 A current transformer, the meter converts 2.5 A with factor 80 to 200 A
MID energy meters: with direct metering the load current flows through the meter, with CT metering a current transformer supplies a small current – the meter calculates back with the CT factor, 80 for 400/5 A.

Calculators and related pages

Typical Applications

Recommended Products

FAQ

What does MID mean for energy meters?

MID is the European Measuring Instruments Directive 2014/32/EU. An MID-compliant active energy meter (annex MI-003) is conformity-assessed from the factory and may be used for billing; the CELSA MID meters are assessed to modules B+D.

Who benefits from MID meters?

Operators who require transparent and reliable consumption data.

Can an MID meter be used with current transformers?

Yes, as a CT-operated meter for 1 A or 5 A secondary, for example DMC6 MID or ECM6 MID. For billing, the current transformers must then also be calibrated, such as the ALO-E plug-on CTs – the MID only covers the meter.

How long is the calibration of an MID meter valid?

In Germany the verification period for electronic electricity meters is 8 years under annex 7 of the MessEV. After that the meter must be re-verified or replaced.